Collie 1
operating WA Western Australia 2024
Total Capacity 219MW
Storage 877MWh
8 Nov, 2:55 am — 11 Nov, 2:55 am AWST
Total Energy --
Capacity Factor --
Net Revenue --
Storage Duration 4 h
Round-trip Efficiency -- Requires interval data
Generation
30 minMarket
About
Collie Battery is Neoen’s first 4-hour long duration battery & its first major project in Western Australia. The project has development approval for 1 GW / 4 GWh.
Collie Battery can provide short-term storage in peak times to ease pressure on the grid. It can charge and discharge 20% of the average demand in Western Australia’s South-West Interconnected System (SWIS).
Stage 1 is sized at 219 MW / 877 MWh
Owner
Units
1
unit