Collie 1
operating WA Western Australia 2024
Total Capacity 219MW
Storage 877MWh
2 — 5 Aug
Total Energy --
Capacity Factor --
Net Revenue --
Storage Duration 4 h
Round-trip Efficiency -- Requires interval data
Generation
30 minPower
MWMarket
About
Collie Battery is Neoen’s first 4-hour long duration battery & its first major project in Western Australia. The project has development approval for 1 GW / 4 GWh.
Once operational, Collie Battery will be able to provide short duration storage in peak times to ease pressure on the grid. It will have the ability to charge and discharge 20% of the average demand in Western Australia’s South-West Interconnected System (SWIS).
Stage 1 is sized at 219 MW / 877 MWh
Owner
Units
1
unit