Located an hour west of Melbourne approximately 15 kilometres south of Ballan, the Yaloak South Wind Farm commenced construction in late 2016 and construction was completed in June 2018, 25 days ahead of schedule.
The project comprises fourteen Senvion MM92 wind turbine generators, rated at 2.05MW each, providing a total installed capacity of 28.7MW with a maximum hub height of 80m and a maximum tip height of 126.25m.
The project has been built in the southern section of the Parwan Valley, which is predominantly cleared agricultural land used for cropping and livestock grazing. Initial plans for a 70 turbine, 115MW capacity wind farm at the site were amended following concerns from local residents of the Parwan Valley about the potential impact on the wedge-tail eagle population and the visual amenity of the local area.